Lección 6/10 · 16 palabras · 0 aprendidas
Concrete and reinforcement
Hormigón y armadura
concreto premezclado, hormigón premezclado
concrete that is mixed at a batching plant and delivered to the site in mixer trucks, ready to use
We ordered 250 cubic metres of ready-mixed concrete for Saturday.
Pedimos 250 metros cúbicos de concreto premezclado para el sábado.
The ready-mixed concrete supplier must provide a delivery ticket for every truck.
resistencia a la compresión
the ability of concrete to resist being crushed, usually tested on samples after 7 and 28 days
The 28-day compressive strength of the column concrete must reach 40 MPa.
La resistencia a la compresión a 28 días del concreto de las columnas debe alcanzar 40 MPa.
Low compressive strength results were found in two of the test cubes.
prueba de revenimiento, ensayo de asentamiento
a simple site test that measures how much fresh concrete sinks when a cone mould is lifted, showing its workability
The site engineer rejected the truck because the slump test result was too high.
El ingeniero de obra rechazó el camión porque el resultado de la prueba de revenimiento fue demasiado alto.
Do a slump test on every truck before pumping starts.
relación agua-cemento, relación a/c
the weight of water divided by the weight of cement in a concrete mix, which strongly affects its strength
Adding water on site increases the water-cement ratio and weakens the concrete.
Agregar agua en obra aumenta la relación agua-cemento y debilita el concreto.
The mix design specifies a water-cement ratio of 0.45.
aditivo, aditivo para concreto
a chemical added to concrete in small amounts to change properties such as setting time or workability
A retarding admixture was used because of the hot weather.
Se utilizó un aditivo retardante debido al clima caluroso.
The admixture dosage must follow the supplier's data sheet.
encofrado, cimbra
temporary moulds made of timber, plywood or steel that hold fresh concrete in shape until it hardens
The formwork for the columns can be removed after 24 hours.
El encofrado de las columnas se puede retirar después de 24 horas.
Check that the formwork is clean and oiled before pouring.
apuntalamiento, entibado
temporary props or frames that support formwork, slabs or excavation sides until they can support themselves
The shoring under the transfer beam must stay for at least 28 days.
El apuntalamiento bajo la viga de transferencia debe permanecer al menos 28 días.
Steel shoring was installed to support the deep excavation walls.
varilla de refuerzo, acero de refuerzo, barra corrugada
steel bars placed inside concrete to make it strong enough to resist bending and pulling forces
The rebar for the slab arrived cut and bent from the workshop.
El acero de refuerzo para la losa llegó cortado y doblado desde el taller.
Rusty rebar must be cleaned before it is placed.
estribo
a small closed loop of steel bar that holds the main bars of a beam or column in place and resists shear
The stirrups near the column must be spaced at one hundred millimetres.
Los estribos cercanos a la columna deben colocarse con una separación de cien milímetros.
Several stirrups were missing at the beam ends, so the pour was stopped.
traslape, empalme por traslape
the length where two reinforcement bars overlap so that force can pass from one bar to the other
The lap splice for these bars must be at least forty times the bar diameter.
El traslape de estas barras debe ser de al menos cuarenta veces el diámetro de la barra.
Do not place all lap splices at the same section of the beam.
recubrimiento, recubrimiento de concreto
the thickness of concrete between the surface and the nearest steel bar, which protects the steel from rust and fire
Use plastic spacers to keep a concrete cover of 25 millimetres.
Use separadores de plástico para mantener un recubrimiento de 25 milímetros.
Insufficient concrete cover led to rust stains on the balcony slab.
planilla de despiece de acero, tabla de doblado de acero
a table listing every reinforcement bar with its mark, size, shape, length and number, used for cutting and bending
The detailer sent the bar bending schedule for the third floor slab.
El detallista envió la planilla de despiece de acero de la losa del tercer piso.
Steel was ordered from the bar bending schedule to reduce waste.
curado, curado del concreto
keeping new concrete wet and at a suitable temperature for several days so that it gains full strength
Curing must continue for at least seven days after the pour.
El curado debe continuar al menos siete días después del vaciado.
The slab cracked because curing started too late on a hot day.
junta de construcción, junta fría
a planned stopping point between two concrete pours, prepared so that the new concrete bonds well to the old
The construction joint in the slab must be at one third of the span.
La junta de construcción de la losa debe ubicarse a un tercio de la luz.
Clean and wet the construction joint before the next pour.
cangrejera, hormigueo, nido de piedra
a defect where the concrete surface has holes and exposed stones because it was not compacted properly
Honeycombing was found at the base of three columns after the formwork was removed.
Se encontraron cangrejeras en la base de tres columnas después de retirar el encofrado.
Poor vibration is the main cause of honeycombing.
